St. Cloud Hospital construction project by the numbers

  • The SCH expansion project will cost $225 million. This includes the north loading dock, ramp and south parking ramp renovations. Target Field cost approximately $412 million. Mall of America cost more than $650 million.
  • SCH’s addition currently is the largest construction project in Minnesota since Target Field.
  • There are 200 construction workers on-site each day.
  • The current hospital building has nine floors (two underground and seven above ground) and is 954,600 square feet (not including the attached CentraCare Clinic - River Campus).
  • The east tower addition will have 10 floors (three underground and seven above ground) and increase the hospital’s size by 360,000 square feet, slightly smaller than CentraCare Health Plaza at 405,000 square feet.
  • The exterior of the new addition will be brick to match the existing structure. When the addition is complete, masons will have laid 625,000 bricks. If these bricks were laid end to end, they would stretch from the hospital to downtown St. Paul – nearly 80 miles.


  St. Cloud Hospital Construction: December 2011
 
  New St. Cloud Hospital East Tower
  October 2011
 
 

Paving of the new service road on the north side of the east addition.

 

 
 

Tearing a wall down.

 

  July 2011
 
 

A mobile scaffold for the bricklayers to lay the brick at the north side of the east addition.

 

 
 

An access hatch to add future air handlers to the top floor.

 

 
 

Sunset over the east addition.

 

  April 2011
 
 

North elevation pre cast exterior.

 

 
 

Preparing to lay brick in the penthouse on the hospital roof.

 

  March 2011
 
 

5th floor.

 

 
 

Framing walls in the operating room.

 

  January 2011
 
 

New addition at night.

 

 
 

Concrete pump.

 

 
 

East elevation finished through A level.

 

 
 

View of the new addition from Sauk Rapids.

 

 
 

View of the addition from the north.

 

 
 

Surgery hallway with a river view.

 

  December 2010
 
 

View of the addition from the north.

 

 
 

Patient floors.

 

 
 

New bridge from the Emergency Trauma Center to the South Ramp.

 

  November 2010
 
 

Exhaust piping for the generator.

 

 
 

North side of the addition.

 

 
 

Duct work being delivered by the truck load.

 

 
 

Exhaust piping for the generator.

 

 
 

Exterior skin of the building is taking shape.



  October 2010
 
 

Surgeons demonstrate the use of a surgical suite in their future space during a site visit.



 
 

Patient floor.

 

 
 

Patient floor.

 

  September 2010
 
 

Patient tower taking shape.

 

 
 

Exhaust piping for the generator.

 

 
 

Landscaping near the cafeteria.

 

 
 

Southeast corner of the addition.

 

 
 

Concrete placing boom pumps concrete onto the deck.



 
 

Pouring the slab on grade in the C Level mechanical room.



 
 

South view of the river from a patient floor.


View photos from previous months

 

CentraCare Health Foundation
1406 Sixth Avenue North
St Cloud, MN 56303
Phone: 320-240-2810
Toll-free: 800-835-6652, ext. 52810
Fax: 320-255-6691
E-mail: foundation@centracare.com
Executive Director
Mark Larkin

 

Home | Site Map | Contact Us | Disclaimer & Privacy Policy | Maps & Directions